Real photo from one of our sites in Dubai
1DrawingsThe bank's copy differs from what was built
2PaymentRejected if the stamp is a copy, not the original
3ElectricityThe wrong filing order blocks completion
4SnagsOne AC drain without a sleeve freezes a payment
Contractor's eye
Eng. Mohamed Shams · Owner's Representative & Advisor

16 years on the contractor's side.Now on yours.

He reads your contract, drawings and payment claims with a contractor's eye, and tells you the truth before you sign.

Move the lens over the villa — see what the contractor sees

Numbers from the records, not from adverts

16
years in contracting
since 2010
65
projects on the company record
villas · towers · clinics · hotels
429
projects studied and priced
from the tender files
28
projects he runs day to day
2022 – 2026
9
consultant offices worked with
in Dubai
232
payments logged in the tracker
a minimum
01 — About

The man who used to sit across the table from you

Eng. Mohamed Shams is the founder and General Manager of Shams Al Nahar Contracting in Dubai. He entered contracting in 2010 and has been on site ever since: pricing, contracting, building, submitting payment claims to banks and to the Mohammed Bin Rashid Housing Establishment, and chasing the consultant, the Municipality and DEWA all the way to the completion certificate.

Sixteen years taught him exactly where a villa gets stuck, and who can get it moving. He knows why every clause was written and where every delay starts.

Today he moves his chair to the other side of the table. He sits next to the owner and uses the same experience in the owner's favour.

Eng. Mohamed Shams
Position
Founder & General Manager — Shams Al Nahar Contracting
Experience
Since 2010 · Dubai
Licence
Building contracting · No. 754113 · since 2016
Focus today
Owner's representative and advisor on building problems
ContractorConsultantOwner Eng. Mohamed
“I know where the contractor falls behind, because I was the contractor.”
02 — Experience over the years

From the first pour to the completion certificate

Every milestone here is backed by a document: a licence, a contract, a certificate or a dated conversation.

  1. 2010

    Started on site

    Entered contracting and learned the work from the ground: steel, concrete, labour and deadlines.

  2. 2016

    Building contracting licence, Dubai

    Shams Al Nahar Building Contracting licence No. 754113 issued on 10 March 2016, followed by electromechanical and building-materials trading licences.

  3. 2022

    28 projects under his daily follow-up

    Since April 2022 he personally runs the follow-up groups with owners and consultants: 26 villas, a G+2 building and a school.

  4. 2023

    Civil Defence completion certificate

    Conversion of a villa into a clinic in Jumeirah — completion certificate issued on 23 November 2023.

  5. ⁦2023–2025⁩

    Citizens' housing villas

    Villa contracts financed by the Mohammed Bin Rashid Housing Establishment and Islamic banks: 11 in Al Awir First, 3 in Wadi Al Shabak, 2 in Al Warqa 4.

  6. 2026

    Completion and handover

    Completion certificate announced for a housing villa in Al Awir on 12 January 2026, a journey that began in 2023.

  7. Today

    On the owner's side

    The same experience, from the other side of the table.

03 — What he learned inside

8 things he learned from the inside

These are not courses. He paid for each one on site.

01

Bank and housing payments

He knows when a claim is accepted and when it bounces: progress percentage, photo order, original stamps and each bank's minimum payment.

02

Drawings and revisions

He checks the approved drawing against what is built, and catches the gap before it turns into demolition and money.

03

Variations and their price

He has priced hundreds of projects. He knows the fair price of an extra item, and when a number is inflated.

04

Consultant approvals

He knows why an approval sleeps at the consultant's office, how to move it, and which missing paper is holding the file.

05

Municipality, DEWA and completion

Filing order matters: one application submitted too early can lock out the next.

06

The owner's VAT refund

He prepares the invoices and stamped receipts the tax authority asks for when an owner reclaims VAT on a new home.

07

Snags and handover

He writes a snag precisely: which room, which item, what exactly is required — so it closes the first time.

08

Rights in writing

No amount leaves without a written undertaking tied to a clear milestone. If it is not written, it did not happen.

04 — Field files

5 real situations. No names.

Each file comes from dated conversations and documents in the company records. Names and plot numbers are removed to protect the owners' privacy.

Field files · 01

The bank's drawing was not the one being built

FROM A DATED CHATMay 2025

The problem

A bank-financed villa had three approved drawing revisions. The copy lodged with the bank had smaller areas, while the columns on site followed the first approval.

What he did

He warned the consultant in writing that building to the old drawing meant breaking a slab, and set the scope and price of the extra work before anything started.

The outcome

The consultant replied: “You are right.” Only the price was left to negotiate.

“You are right.”the consultant's reply

Lesson for owners

Always ask: which revision does the bank hold, and which one is being built?

Field files · 02

A villa idle for two months over an electrical approval

FROM A DATED CHATMarch 2025

The problem

The electrical approval was stuck at the consultant's office and the site had stopped. The drawing that finally arrived had no load schedules.

What he did

He escalated in writing and found that the drawing belonged to a different villa. He then warned that filing for completion first would close the file and block the electrical change, and set the right filing order.

The outcome

The electrical issue was solved and the consultant stamped the completion request.

Lesson for owners

The delay is not always the contractor's. Sometimes it is one paper at the consultant's office.

Field files · 03

The bank released 95K of a 150K payment

FROM A DATED CHATJune 2026

The problem

A villa financed by two banks. One bank paid less than the certified amount and rejected another claim because the consultant's stamp was a copy.

What he did

He explained the bank's minimum-payment rule, moved the next claims to the second bank file, and offered a guarantee cheque against any amount released ahead of its work.

The outcome

The consultant accepted the route and the guarantee cheque.

Lesson for owners

Every bank has its own rules. Knowing them saves you weeks.

Field files · 04

A tax authority deadline about to expire

FROM A DATED CHATJune 2026

The problem

An owner reclaiming VAT on his home was asked for a total-VAT invoice and a stamped receipt voucher before the deadline.

What he did

He issued the invoice and the receipt that same night, stamped them the next morning, then opened the owner's DEWA application.

The outcome

The owner replied: “Thank you, Mohamed.”

“Thank you, Mohamed.”the owner's reply

Lesson for owners

The VAT refund is your right, but it needs the contractor's paperwork. Ask for it from day one.

Field files · 05

The funder's 10% rule

FROM A DATED CHATMarch 2026

The problem

The funder accepts a payment only when progress reaches 10%, and rejects bathroom photos without first-fix plumbing.

What he did

He re-sequenced the site: first-fix plumbing, water and paint primer first, photographed in the order the reviewer accepts.

The outcome

The payment was approved.

“Approved.”the approval message

Lesson for owners

A payment is sometimes late because of the order of work, not the amount of it.

05 — Check your problem

Where is your villa stuck?

Pick the closest description. You get the papers to prepare and the first 3 steps — free, no sign-up.

Prepare these papers

    First 3 steps

      Through the contractor's eye
      Send my case to Eng. Mohamed General guidance based on field experience, not legal advice.
      06 — How he works with you

      4 steps. No surprises.

      1. 1

        Diagnosis

        Bring your papers: contract, drawings, payments, correspondence. He reads them and tells you where you stand.

      2. 2

        Position report

        One written page: what you are owed, what you owe, and where the risk is.

      3. 3

        Action plan

        Whom to address, with which paper, in which order: contractor, consultant, bank, Municipality.

      4. 4

        Follow-up to handover

        He attends meetings with you and reviews every payment and every snag before you sign.

      Limits of the role

      • He is not a lawyer and does not represent you in court.
      • He does not replace the supervising consultant approved by the Municipality — he works with them in your favour.
      • He takes no commission from any contractor or supplier.
      • He does not represent an owner on a project built by Shams Al Nahar — to avoid any conflict of interest.

      From our sites

      Real photos from villa projects in Dubai, 2026.

      Glazed façade — external finishing stage
      Glazed façade — external finishing stage
      Plastering and elevations
      Plastering and elevations
      Cantilevers and projecting beams
      Cantilevers and projecting beams
      Eng. Mohamed Shams

      Villa stuck? Let someone who knows the game read your papers.

      Send a short description of the problem on WhatsApp. Eng. Mohamed replies personally.